Who Built How Many Dams In Pakistan? Comparison and Facts. Data and Facts Compiled By Dr. Humma Saifullah
کیا آپ کو علم ہے کہ
ایوب خان کے 11سالہ دور میں 3بڑے ڈیم بنے
ضیاالحق کے 10سال میں 8ڈیم
مشرف کے 9سالُ میں 3 ڈیم
بینظیر کے دور میں ٹوٹل 5 ڈیم
اور نواز شرئف دور میں 11 بڑے ڈیم بنے
پاکستان کُی کل بجلی پیداوار کا تقریبا 40 فیصد ن دور میں نیشنل گرڈ میں شامل ہوا
1958-69
1961 waliltangi dam
1967 Mangla
1974 tarbela dam
1978-88
1979 hub dam
1982 Mangi dam
1983 shadak dam
1984 khud koocha
1985 under base dam
1986 thamarak dam
1987 amach dam
1988 shaiker dam :
1990-93
1991 khajeer dam
1991 tooth dam
1993 shagai dam
1993 sasnak mana storage
1993-96
1994 band e chaman
1994 nishpa dam
1994 pinakai dam
1994 tabai dam
1995 akra kaur
1997-99
1995–96 hingi dam
1997 Tangi dam
1999-08
2002 chotiari dam
2006 Mirani Dam
2007 sabaqzai dam
2008-13
2011 dandy dam
2013-18
2013 satpara dam
2014 drawat dam۔ 2010
2015 Noulong dam
2018 neelam jehlum
2019 nai gaj :
Disclaimer: Might be slight error in completion years mentioned since i pulled the data from a lot of sources :
Dam Projects by Imran Khan Led PTI Govt In Pakistan. Compiled By PTI Family Magazine On Twitter.
2/n
Darawat Dam
Construction of the rain fed dam started - January, 2012 Cost = Rs11.67bn
Completed in 2014
(Ref https://t.co/jggjqMivsk)
This is a failed project and was first time overflowed since it’s inception in 2014.
(Ref dated 27 July 2022
3/n
Performance Audit Report 2016-17 states
Darawat Dam Project was approved by ECNEC at a cost of Rs. 7,554.69 million.
Major changes were made in the design
Power house having capacity of 300 KW was not constructed which
resulted in heavy loss to the WAPDA
4/n
State-land was not distributed among the landless women
Government of Sindh did not take interest in construction of Phase-II of Darawat Dam Project being its own responsibility
High Efficiency Irrigation System was not developed by the Government of Sindh
5/n
EPC Contractor did not follow the design provided in the Feasibility Report
Main contract was awarded at 137.93% higher rates from the approved cost of PC-I i.e. Rs. 3,175.20 million
Contract was awarded without competitive bidding
(Ref https://t.co/3V9VGiJc9S)
6/n
Naulong Dam is an embankment dam currently under construction on the Mula River, about 30 km from Gandawah City in Jhal Magsi district of Balochistan, Pakistan.
Feasibility studies completed in 2009
Planned completion in 2012 remains unbuilt by 2022
https://t.co/idjkv1P8Et
7/n
Neelum–Jhelum Hydropower Plant
Approval 1989
Project was intended to begin in 2002 &be completed in 2008
Construction started - 2008
Contract - July 2007.
1st generator - commissioned in April 2018
Project - completed in August 2018
(Ref https://t.co/fmM5bpFEoI)
8/n
Nai Gaj Dam
Construction started - May 2012. Planned to be completed in 3 years,
Project heavily delayed, increased cost from an estimate of Rs17 Billon to a revised Rs 47.7 Billion in 2019. Around 51% of the construction work completed in 2018.
expected completion in 2024
9/9
Little efforts to go through WAPDA Papers, newspapers, wikipedia etc. If any information is found wrong, kindly update thread and correct the details.
But none of the new Hydel Project was started between 2013-2018, Even few projects are still not completed started by PPP